This PMP formulas cheat sheet covers every calculation that commonly appears in PMP prep: earned value, forecasting, estimating, float, communication channels, risk, procurement and project selection. Each formula comes with a worked example and one line on what the answer means. If you only learn five, learn these: CV = EV − AC, SV = EV − PV, CPI = EV / AC, SPI = EV / PV and EAC = BAC / CPI. Every number below was recalculated for this page, and the earned value examples all use one project, so you can see how the formulas connect. A compact printable table sits near the end.
How much math is on the 2026 PMP exam?
PMI does not publish a formula list or a count of math questions. What the July 2026 exam content outline does say is telling. Under the Process task "Plan and manage finance", it lists "quantify risk and contingency financial allocations", "monitor financial variations" and "manage financial reserves". Under "Plan and manage schedule" it lists estimating with milestones, dependencies and story points, and "analyze schedule variation". Under "Evaluate project status" it asks you to measure, analyze and update project metrics.
The exam also added graphic-based questions, where you interpret charts, graphs or diagrams, and case sets that may include charts. So expect to read an earned value chart or a burndown and decide what it means, more than to grind long arithmetic. Prep vendors guess at the number of pure calculation questions, but none of those estimates come from PMI, so treat them with care. At a test center you get a calculator built into the exam, and you can ask for a handheld one, according to PMI's Certification Handbook. There is no formula sheet, so you need to know these by heart. That is why this PMP formulas cheat sheet pairs every formula with what its result means, not just the arithmetic.
Earned value basics: PV, EV, AC and BAC
Here is the project used for every earned value example on this page. A website build has a budget at completion (BAC) of $200,000. At the month-4 status date, the plan said the team should be 40% done. In fact it has finished 36% of the work and spent $90,000.
| Term | Formula | Worked example | Meaning |
|---|---|---|---|
| Budget at completion (BAC) | Total approved budget | $200,000 | What the whole project should cost |
| Planned value (PV) | Planned % complete × BAC | 0.40 × 200,000 = $80,000 | Value of work scheduled by now |
| Earned value (EV) | Actual % complete × BAC | 0.36 × 200,000 = $72,000 | Value of work actually done |
| Actual cost (AC) | Money spent to date | $90,000 | What the done work really cost |
A quick sanity check: the project is 36% done (EV / BAC) but has spent 45% of its budget (AC / BAC). That gap is the story the rest of the formulas tell.
The PV naming trap
"PV" means planned value in earned value questions and present value in project selection questions. The context tells you which. If the question mentions an interest or discount rate, it is present value.
Variances and performance indexes
Variances are differences in dollars. Indexes are ratios. Both always start with EV.
| Formula | Expression | Worked example | Meaning |
|---|---|---|---|
| Cost variance (CV) | EV − AC | 72,000 − 90,000 = −$18,000 | Negative means over budget |
| Schedule variance (SV) | EV − PV | 72,000 − 80,000 = −$8,000 | Negative means behind schedule |
| Cost performance index (CPI) | EV / AC | 72,000 / 90,000 = 0.80 | 80 cents of value for each dollar spent |
| Schedule performance index (SPI) | EV / PV | 72,000 / 80,000 = 0.90 | Progressing at 90% of the planned rate |
The memory rule: a negative variance or an index below 1 is bad news; a positive variance or an index above 1 is good news. Our example has CPI and SPI at different values on purpose, so you can tell them apart in a question that gives you both.
Forecasting: EAC, ETC, VAC and TCPI
Estimate at completion (EAC) is the expected total cost when the project ends. There are four versions, and exam questions usually signal which one to use through a phrase about the future.
| EAC version | Expression | Worked example |
|---|---|---|
| Current CPI continues | BAC / CPI | 200,000 / 0.80 = $250,000 |
| Variance was a one-off | AC + (BAC − EV) | 90,000 + 128,000 = $218,000 |
| Original estimate flawed | AC + bottom-up ETC | 90,000 + 140,000 = $230,000 |
| CPI and SPI both matter | AC + (BAC − EV) / (CPI × SPI) | 90,000 + 128,000 / 0.72 = $267,777.78 |
The $140,000 bottom-up figure is an assumed re-estimate of the remaining work, given for the example.
Which EAC formula to use
- Estimate no longer valid?Use AC plus a new bottom-up ETC.
- Overrun was a one-off?Use AC + (BAC − EV); the rest goes to plan.
- Cost trend will continue?Use BAC / CPI. This is the default.
- Schedule pressure too?Use AC + (BAC − EV) / (CPI × SPI).
ETC, VAC and TCPI
Using the default EAC of $250,000:
| Formula | Expression | Worked example | Meaning |
|---|---|---|---|
| Estimate to complete (ETC) | EAC − AC | 250,000 − 90,000 = $160,000 | Money still needed |
| Variance at completion (VAC) | BAC − EAC | 200,000 − 250,000 = −$50,000 | Expected overrun at the end |
| TCPI to hit BAC | (BAC − EV) / (BAC − AC) | 128,000 / 110,000 = 1.16 | Must work 16% more efficiently than plan |
| TCPI to hit EAC | (BAC − EV) / (EAC − AC) | 128,000 / 160,000 = 0.80 | Equal to the current CPI, so achievable |
To-complete performance index (TCPI) answers one question: how efficient must the remaining work be to land on a target? Above 1 means you must do better than you have so far, which is hard when CPI is 0.80. That is often the point of the question. If TCPI against BAC is well above the current CPI, the budget is unlikely to hold, and the right answer usually involves asking for a revised budget through change control.
Estimating: PERT, triangular and standard deviation
Three-point estimates use optimistic (O), most likely (M) and pessimistic (P) durations. Example: O = 4, M = 6, P = 14 days.
| Formula | Expression | Worked example | Meaning |
|---|---|---|---|
| PERT (beta) estimate | (O + 4M + P) / 6 | (4 + 24 + 14) / 6 = 7.0 days | Weights the most likely value four times |
| Triangular estimate | (O + M + P) / 3 | (4 + 6 + 14) / 3 = 8.0 days | Simple average of the three |
| Standard deviation (σ) | (P − O) / 6 | (14 − 4) / 6 = 1.67 days | Spread of the estimate |
| Variance | σ² | 1.67² ≈ 2.78 | Add variances, not σ, along a path |
The triangular estimate is higher here because the pessimistic value is a long tail. That holds whenever O + P is more than 2M. If O + P is less than 2M, PERT comes out higher instead, so do not memorize "triangular is always bigger".
For ranges, courses use the normal-distribution rule of thumb: about 68.3% of outcomes fall within ±1σ, 95.4% within ±2σ and 99.7% within ±3σ. Here, ±1σ gives 5.33 to 8.67 days and ±2σ gives 3.67 to 10.33 days.
Schedule: float and the critical path
Total float is how long an activity can slip without delaying the project: LS − ES, or LF − EF. With ES on day 5 and LS on day 8, total float is 3 days. Activities with zero total float are on the critical path.
Free float is how long an activity can slip without delaying its next activity: ES of the successor minus EF of the activity. If the activity finishes on day 9 and its successor can start on day 11, free float is 2 days. This uses the convention in which a successor can start on the same number its predecessor finishes on. If your course numbers days so that the successor starts the day after, subtract one more.
Communication, risk and procurement
Communication channels. With n people, there are n(n − 1) / 2 channels. A team of 12 has 66. Add three people and you have 105, an increase of 39. Questions often ask for the increase, so read the stem twice.
Expected monetary value (EMV). Multiply each risk's probability by its impact and add them up, with threats negative and opportunities positive. A 30% chance of a $40,000 loss and a 20% chance of a $25,000 gain give 0.30 × −40,000 + 0.20 × 25,000 = −$7,000. That is the kind of figure behind the outline's "quantify risk and contingency financial allocations".
Point of total assumption (PTA). In a fixed-price-incentive-fee contract, PTA = (ceiling price − target price) / buyer's share ratio + target cost. With a target cost of $100,000, a target fee of $10,000 (so a target price of $110,000), a ceiling of $120,000 and an 80% buyer share: 10,000 / 0.8 + 100,000 = $112,500. Above that cost, the seller absorbs every extra dollar.
Project selection formulas
These matter less on the current outline, which focuses on running projects rather than choosing them. That is our judgment, not a PMI statement, so learn them but give them less time.
- Present value: FV / (1 + r)ⁿ. $121,000 received in two years at 10% is worth 121,000 / 1.21 = $100,000 today. Net present value subtracts the investment.
- Benefit-cost ratio: benefits / costs. $300,000 / $200,000 = 1.5. Above 1 is favorable.
- Payback period: investment / annual net cash inflow. $120,000 / $30,000 = 4 years. Shorter is better.
Agile numbers
With about 60% of questions set in agile or hybrid contexts, velocity math is worth knowing. Forecast sprints as remaining story points divided by velocity: 120 points at 30 points per sprint is 4 sprints. On a burndown chart, a line above the ideal trend means the team is behind; a flat stretch means no work was accepted in that period.
Printable PMP formulas cheat sheet
This compact table is the PMP formulas cheat sheet in one place. Print this page or save it as a PDF; no sign-up needed.
| Formula | Expression | Good result |
|---|---|---|
| CV | EV − AC | Zero or positive |
| SV | EV − PV | Zero or positive |
| CPI | EV / AC | 1 or above |
| SPI | EV / PV | 1 or above |
| EAC, default | BAC / CPI | At or below BAC |
| EAC, one-off | AC + (BAC − EV) | At or below BAC |
| EAC, new estimate | AC + bottom-up ETC | At or below BAC |
| EAC, CPI × SPI | AC + (BAC − EV) / (CPI × SPI) | At or below BAC |
| ETC | EAC − AC | — |
| VAC | BAC − EAC | Zero or positive |
| TCPI (BAC) | (BAC − EV) / (BAC − AC) | 1 or below |
| TCPI (EAC) | (BAC − EV) / (EAC − AC) | 1 or below |
| PERT | (O + 4M + P) / 6 | — |
| Triangular | (O + M + P) / 3 | — |
| σ (beta) | (P − O) / 6 | Smaller is tighter |
| Total float | LS − ES or LF − EF | Zero means critical |
| Free float | ES of successor − EF of activity | — |
| Channels | n(n − 1) / 2 | — |
| EMV | Sum of probability × impact | — |
| PTA | (Ceiling − target price) / buyer share + target cost | — |
| Present value | FV / (1 + r)ⁿ | — |
| BCR | Benefits / costs | Above 1 |
| Payback | Investment / annual net inflow | Shorter |
| Sprints left | Remaining points / velocity | — |
How to make a PMP formulas cheat sheet stick
Reading a cheat sheet feels productive, but recognizing a formula is not the same as recalling it under time pressure. Two habits make the difference. Retrieval: cover the expression column and write each formula from memory, then check. Spacing: come back to the ones you missed a day later, then a few days after that, instead of rereading the whole sheet every night.
CramClip does both from your own material. Upload this page saved as a PDF, or your course's formula notes, and it builds a short two-host audio lesson that explains each formula and when to use it. A four-question quiz follows each lesson. Anything you miss becomes a review card that returns one, three, seven and fourteen days later. It is an iOS app, the first lesson is free, and it is not a PMI product or a question bank.

Frequently asked questions
Are formulas on the new PMP exam?
PMI does not publish a count of math questions. The July 2026 outline does include analyzing schedule and financial variation and measuring project metrics, plus graphic-based questions that ask you to read charts.
Do I get a formula sheet or a calculator in the PMP exam?
There is no formula sheet. PMI says a calculator is built into the computer-based exam and you can ask the test center for a handheld one.
Which EAC formula is used most often?
BAC divided by CPI, which assumes current cost performance continues. Use another version only when the question signals a one-off variance, a new estimate, or schedule pressure.
What does a TCPI above 1 mean?
The remaining work must be done more efficiently than the work so far for the project to hit its target. The further above 1, the less realistic the target.
Should I use PERT or triangular estimates?
Use whichever the question names. PERT weights the most likely value four times; triangular is a plain average of the three estimates.
Sources
- PMI. Project Management Professional (PMP) Examination Content Outline – July 2026.
- PMI. Certification Handbook, revised June 2026 (calculator policy).
- PMI. The new PMP exam.
- Brain Sensei. 15 PMP exam formulas you need to know.
